Before you sign your 2027 quotes: review the hours of three finished projects

20 November 2026 3 min read Mataee

Before you sign your 2027 quotes: review the hours of three finished projects

Photo by Hendrik Morkel on Unsplash

Late November, quote requests for next year start coming in. You open the last comparable quote, adjust two lines and send it. The trouble is that this quote may already have been wrong. If the project took more hours than planned, you have just carried the same gap forward for another year.

Pick three projects, not thirty

There is no need to analyse the whole year. Take three finished projects that are typical of what you sell most often: a small one, a medium one and a large one. They should be closed, so the hours are complete, and recent, so they reflect how you work today.

For each one, write down two numbers: the hours planned in the quote and the hours actually spent. If you track time by project, the second number takes a few seconds to read. If you don't, all you have is an impression, and that impression is exactly what produced the original quote.

Look at where the gap goes

The total is not enough. A project planned at 80 hours and finished at 100 teaches you nothing until you know where the 20 extra hours went.

Split it by main stage, depending on your trade: design, production, acceptance testing, client communication. The gaps nearly always sit in the same place from one project to the next. If acceptance testing overruns every time, it is not an accident, it is an underestimated line in your quote.

Take an example. On three projects, acceptance testing was planned at 10, 16 and 24 hours, and you spent 15, 24 and 36 hours on it. The gap is the same everywhere: 50% more. Your next quote should therefore count one and a half times what you would have written on that line by instinct.

The article on how to estimate time for a quote explains how to build those lines.

Correct the next quote, not the old one

Do not rewrite the history of finished projects. Simply apply the coefficient you observed to the relevant lines of your next quotes, and keep a record of the rule: "acceptance testing: estimate multiplied by 1.5".

In Mataee, a milestone carries an hour budget: by creating one milestone per main stage on your 2027 projects, you will have the same comparison next year without having to piece anything together.

This week, pull the hours of three finished projects and work out the gap on a single stage, the one that seems to overrun most often.